Tofoo Breaks Ground on Malton Factory Built to Double Capacity

The Tofoo Co has begun building a new manufacturing base at Malton Enterprise Park in North Yorkshire, a move designed to double its initial production capacity and remove a looming constraint from leases that expire in 2028. The company announced the project on 22 October 2026; construction had started in September, and occupation is planned for autumn 2027.
The facility is intended to support more than 10,000 tonnes of annual tofu output and £73 million in sales by 2033. Productive space will be about 3.5 times the current footprint, while one-quarter of the new site's otherwise unallocated area will be reserved for future lines. Those details make the project more than a routine property move: it is a deliberate capacity platform for growth in the United Kingdom and continental Europe.

What is being built
Harrison Developments Malton LLP is leading the development and build. The completed site is expected to combine production space with a development kitchen and pilot plant, giving the manufacturer room to test products and host customer work without interrupting full-scale lines. The announced design also includes solar panels, electric-vehicle charging points and heat-recovery systems.
Financing is being provided by HSBC UK alongside existing shareholders, management and Comitis Capital, the German investment firm that acquired a majority stake in Tofoo in 2024. The company has not disclosed the project's total capital cost, the split between debt and equity, equipment suppliers, or a firm number of jobs to be created. Apprenticeships have been described as part of its people-development plans, but no quantified hiring commitment has been announced.
Project measure | Disclosed position | Why it matters |
Construction | Started September 2026; completion targeted for autumn 2027 | Leaves roughly a year before current leases expire in 2028 |
Initial capacity | About twice the present level | Creates headroom before the 2033 volume target |
Productive space | About 3.5 times the current footprint | Allows less congested operations and more line flexibility |
2033 ambition | More than 10,000 tonnes and £73 million in sales | Sets a measurable utilization and revenue benchmark |
Expansion reserve | 25% of unallocated space held for future lines | Reduces the need for another near-term site move |
The £73 million target implies a high-value product mix
Dividing £73 million by 10,000 tonnes gives £7,300 per tonne, or £7.30 per kilogram. Because the company says output will exceed 10,000 tonnes, the implied average falls below £7.30 per kilogram if sales remain £73 million. This is not a retail-price forecast: it is a rough measure of net sales per unit of site-supported output, and the actual figure will depend on product format, customer mix, exports and the share of higher-value prepared foods.
The comparison nevertheless helps explain why the factory includes development capacity rather than only larger tofu lines. A business trying to reach the sales target solely by pushing commodity-style blocks would face a different margin and utilization challenge from one that adds seasoned, frozen or prepared products. The reserved floor space and pilot plant keep both routes open.
A growth plan built around a lease deadline
The current Malton operation uses leased buildings that the company describes as space-constrained, with leases due to expire in 2028. Moving into the new plant in autumn 2027 would provide a buffer for commissioning, validation and customer approvals before the old sites must be vacated. That sequencing is operationally important: a delayed handover could compress the time available to qualify equipment and transfer products without supply disruption.
Tofoo's founders, David Knibbs and Lydia Smith, built the company from a small artisan producer acquired in 2015. In an April 2026 Financial Times interview, Knibbs said the business had annual revenue above £23 million and that the wider group employed about 170 people. He also said the founders had bought back a 6% holding after the 2024 sale to Comitis and remained involved in leadership. Against that recent revenue figure, £73 million is more than three times larger, although the two numbers refer to different dates and the 2033 target may reflect a broader product and market mix.
Why this matters beyond one tofu brand
The UK plant-based category has been uneven, with several heavily processed meat-alternative businesses retrenching after rapid expansion. Tofu sits in a different part of the market: it is an established soy food with a short core ingredient list and demand across Asian cuisines as well as vegetarian and flexitarian diets. Tofoo's investment should therefore not be read as proof that every plant-based segment has returned to growth.
It does show that a focused manufacturer is willing to commit to a larger dedicated asset, backed by a bank and private-equity owner, when existing space and leases constrain the business. The project also shifts the company's risk profile. Today the main constraint is capacity and fragmented space; after commissioning, the challenge will be filling a much larger operation quickly enough to cover fixed costs while maintaining quality and service.
What to watch before the 2027 move
Four milestones will determine whether the announced scale becomes productive capacity rather than unused floor space. First is practical completion on schedule. Second is successful commissioning and food-safety validation of the production lines. Third is evidence of customer commitments in the UK and Europe that support utilization. Fourth is disclosure of employment, energy use and actual output once the plant is running.
The headline targets are clear, but the most decision-useful figures are still missing: total capex, installed tonnes per hour, the number of shifts, expected headcount and the balance between base tofu and higher-value prepared products. Those disclosures would allow suppliers, lenders and competitors to judge whether the factory is primarily a replacement site, a European export hub, or both.
Sources and methodology
Agrilinkage reviewed the same-day project report and disclosed capacity figures, a separate UK report carrying the developer and company statements, Tofoo's official company history, and the Financial Times interview for recent ownership, employment and revenue context. The £7.30-per-kilogram figure is Agrilinkage's calculation from the company's stated £73 million sales and 10,000-tonne benchmarks; it is presented only as an implied average at exactly 10,000 tonnes.